869-465-2000
869-466-7308
869-465-2013 / 600
869-465-2000

Surcharge Calculations

where,     FCAF = The Fuel Cost Adjustment Factor (Fuel Surcharge)
A = Current Month’s Average Fuel Price (EC$/IG)
B = Average Fuel Price at Base Tariff (EC$/IG)
C = Current Month’s Fuel Usage
D = Current Month’s Electricity Production (kWh)

Other Services Fees

ServicePrice (EC)
Meter Test$10.00
Removal of Meter$25.00
Removal of service line$25.00
Inspection$25.00
Inspection from single Phase to 3 phase$75.00
Upgrade of service$25.00
Reconnection (Residential)$100.00
Reconnection (Commercial)$250.00
Temporary Supply:
Socket outlet$45.00
Flood lights$100.00