Scheduled Maintenance Outages for 7th – 11th March 2022
Basseterre, St. Kitts (3rd March 2022)—The St. Kitts Electricity Company Ltd. is advising the public of scheduled maintenance outages for the week Monday 7th March – Friday 11th March. The scheduled maintenance outages are necessary to perform maintenance as a part of our ongoing efforts to improve reliability.
DATE | TIME | AREA(S) TO BE AFFECTED |
Monday 7th March 2022 | 9:00am-3:00pm | Ottleys Housing, The Grange, Sea Breeze Manor, Lodge |
9:00am-11:00am | Frigate Bay: The Strip | |
Tuesday 8th March 2022 | 9:00am-3:00pm | Upper Cayon, Tank, Sarah Bowry, St. Mary’s Terrace, Lovers Lane, Cabbage Tree |
9:00am-11:00am | Boureaux Commercial | |
Wednesday 9th March 2022 | 9:00am-3:00pm | Sky Academy, Canada Estate, Key’s East Housing |
9:00am-1:00pm | St Pauls, Rawlings Housing | |
Thursday 10th March 2022 | 9:00am-3:00pm | Parsons Ground |
Friday 11th March 2022 | 9:00am-1:00pm | Upper Monkey Hill |
9:00am-11:00am | Cedar Grove, Milliken |
Customers in these communities can expect an interruption of supply between the hours stated. Please note that the electricity supply may be interrupted later and restored earlier than the scheduled times.
SKELEC apologizes for any inconvenience caused by these electricity supply interruptions. Persons who remain without power after the scheduled outages are asked to call 465-2013 or 600 from a mobile phone to report the outage.
The St. Kitts Electricity Company Ltd. would like to thank the public for its understanding and support during this time.